MLFC Infrastructure upgrade

Logo
  • Works of major plant refurbishment and enhancement to improve resilience.
  • Full programme of repairs and improvement to corporate buildings in full occupation.
  • As part of our appointment we were commisssioned to provide the full range of duties required of a CDM Co-ordinator.
  • The current replacement of seven chillers providing 8MW cooling to their London headquarter business and main trading centre, the works are being undertaken whilst the building is live and the scheme includes for energy efficiency, logistics and risk management of the scheme, crainage, temporary cooling plant and temporary modifications to the base build scheme to keep the facility live with a robust temporary engineering solution.
Tweet about this on TwitterShare on LinkedInEmail this to someone