FCP 2013 – Appold Street

Logo
  • As part of the Deutsche Bank facilities capital plan works for 2013, Hurley Palmer Flatt were appointed to undertake the works at Appold Street.
  • Works included CWS tank replacement, battery replacement for the emergency lighting UPS system, upgrade of the leak detection systems and replacement of the flow switches.
  • Each element of works involved the surveying of the appropriate services in order to develop the brief into a detailed design and tender package.
  • The contractor undertook the replacement works over a four month period.